Users with permission level of Quality Owner, Approver and Editor can extend CAPA due dates. 

Unapproved CAPA phase
To extend a CAPA Phase Due Date for a phase that is not yet approved, click Extension Requests from the Phase of the CAPA in which the extension is being requested. 

Enter the new phase 1 due date you are requesting and a justification for the change.
The approvers that are shown are based on the permissions set by your Quality Owner/Amin.

Approved CAPA Phase
To extend a phase due date for a CAPA phase that has already been approved, first click on the Edit icon and then click on Extension Requests

Enter the new phase 1 due date you are requesting and a justification for the change. The approvers that are shown are based on the permissions set by your Quality Owner/Amin. 

When you are done, click on Submit Extension Request and it will be routed for approval. 


If you have any questions, you can reach us through the chat or email us at
support@enzyme.com. 